Project
Current status
The school was officially opened on the 14th September 2010. Our aim now is to secure the monthly expenditure of the school and to advance the construction of the missing classrooms.Monthly Costs
| teachers' salary | 360 € |
| meal (30 Cent pro Tag pro Kind) | 450 € |
| Salary of the Secretary und Security | 110 € |
| electricity and water | 60 € |
| Cleaning & maintenance | 50 € |
| Monthly Costs Total | 1030 € |
Construction of new classrooms
Our next goal is to build the missing three classrooms on the new property, that was given us by the Mayor of Bobo-Dioulasso. All funds, which go beyond the coverage of the monthly costs will be flowing into the construction.⇑top
Project History
2002-2004

- Foundations for the accommodation of the teachers - A small building to house the workers and the caretaker.
2006 – 2008

- Completion of the caretaker's house (roof). - Purchase of materials for bricks (cement, sand, pebbles & water) - Production of bricks - Construction of the foundations for two classrooms
2009


- Completion of all 3 classrooms + roof - Interior ceiling in all buildings - Interior and exterior plaster for all rooms (the colored paint is still missing) - Manufacturing windows and doors, including the entrance gate - Building of toilets - Order for production of school furniture - Manufacturing of tiles for the schoolyard - Laying power supply lines
2010


(2009)/2010 we managed to raise the necessary funds to finish the school with 3 class rooms: + laying water supply pipes + making toilet doors + Painting of windows, doors and the exterior walls. The school was officially opened on the 14th September 2010. See photo album and Video
2010-10-04 1st Day Of School